Macon Campus Traffic Re-routed Due to Construction
January 30, 2006
For More Information:
Mercer Police
(478) 301-2970
Due to construction at the new Science and Engineering Bldg site, traffic on College and Prince Streets will have to be rerouted. In order to minimize the inconvenience, construction on these streets will be completed in two phases:
Phase 1 - Feb 4th thru Feb 24th - Prince Street will be blocked between the Mercer Health Systems parking lot and College Street. To view a map of the affected area and the alternate route, please click on the following link:
Phase 2 - Feb 24th thru April 15th - The south end of College Street will be blocked between Prince Street and the entrance to the parking lot above the School of Engineering. To view a map of the affected area and the alternate route, please click on the following link:
Detour signs will be put in place at the end of this week to to guide everyone from the South Campus entrance of College Street (at Mercer University Drive) to the North Campus entrance of College Street (at Coleman Avenue). Questions should be directed to Mercer Police at 478-301-2970.
|